Nice
Nice hydroelectric overview.
Niçë is an operating hydroelectric installation on the Velçan stream in south-eastern Albania. The concession company MP-HEC holds the generation licence, and the plant connects to the distribution network through Lozhan substation.In OperationAlbania
At a Glance
Other capacity
2.3 MWOwners
Energy Albania Group sh.p.k. +1 moreOperator
Data coming soonCountry
AlbaniaLocation
40.768°, 20.569°Website
Data coming soonOwnership
3 records| Share | Organisation | Role | Details | Period |
|---|---|---|---|---|
| Unknown | Indirect Parent | The April 2024 company extract identifies Energy Albania Group as the sole shareholder of MP-HEC. This is ownership of the project company. | Current / not dated | |
| Unknown | Project Company | MP-HEC is the licensed concession company for the Niçë hydroelectric installation. | Current / not dated | |
| Unknown | Operator | MP-HEC is the licensed electricity producer recorded against Niçë in ERE’s production register. | Current / not dated |
Organisations
14 recordsOrganisations recorded as working on this asset or its project, and their role.
| Organisation | Role | Details |
|---|---|---|
| Historical preliminary investor and loan counterpartyFinance Insurance Legal | Entered a preliminary share-purchase agreement and associated loan in March 2015, then withdrew from the proposed acquisition in June 2015. The resulting financial dispute was considered by Albanian courts. | |
| Original concession participantHistorical Development Context | The 2 February 2009 Niçë concession was concluded with the temporary consortium of DEVY and ZYFI, the former name of KEFA. | |
| Electricity generation licensing authorityRegulatory Permitting | Granted and subsequently amended the Niçë generation licence, including the September 2025 removal of earlier document-submission conditions. | |
| Shareholder of the project-company parentDevelopment And Asset Management | The April 2024 Albanian company records identify ETRA S.r.l. as a 50% shareholder of Energy Albania Group, the parent of MP-HEC. | |
| Shareholder of the project-company parentDevelopment And Asset Management | The April 2024 Albanian company records identify Ghiggia Ingegneria d’Impianti S.r.l. as a 50% shareholder of Energy Albania Group, the parent of MP-HEC. | |
| Original concession participantHistorical Development Context | The 2 February 2009 Niçë concession was concluded with the temporary consortium of DEVY and ZYFI, the former name of KEFA. | |
| Original concession contracting authorityConcession And Project Tracking | The Ministry of Economy, Trade and Energy was the contracting authority for the Niçë BOT concession signed on 2 February 2009. | |
| Improved project-design approval authorityConsenting And Permitting | ERE’s 2019 licence decision records the ministry’s approval of the improved implementation design and subsequent documentation requirements. | |
MP-HEC sh.p.k | Operator | Not set |
| Licensed hydroelectric concession companyProject Company And Development | Holds the Niçë generation licence and operates the hydroelectric installation under the concession framework. | |
| Municipal land-use lessorLease Award And Site Control | ERE’s licence documentation records a municipal forest and pasture land-use lease signed on 12 December 2016 for the Niçë project. | |
| Municipal land-use lessorLease Award And Site Control | ERE’s licence documentation records a municipal forest and pasture land-use lease signed on 28 September 2017 for the Niçë project. | |
| Historical distribution-connection approvalGrid Connection | Issued the October 2017 approval for connection through the 35/6 kV busbars at Lozhan substation. | |
| Historical water-use authorisation issuerConsenting And Permitting | Issued water-use authorisation VI/5 on 17 February 2010 for the original Niçë design on the Velçan stream. |
Capacity history
Recorded project capacity figures. Future-dated changes are shown but are not used as current capacity.
| Effective | Capacity type | Capacity | Source |
|---|---|---|---|
| 24 Oct 2017 | Other capacity | 2.3 MW | ERE — historical OSHEE grid-connection approval of 24 October 2017 |