OranjeWind installs first offshore wind monopile
RWE and TotalEnergies have installed the first monopile at the 795 MW OranjeWind offshore wind farm in the Dutch North Sea, starting construction of 53 foundations. Monopile installation is due by early 2027, turbine installation during 2027 and full commissioning in 2028.