Arauco II – Phases III and IV (PEA III)
Arauco II – Phases III and IV (PEA III) onshore wind overview.
PEA III comprises phases III and IV of Arauco II, near Aimogasta in Argentina’s La Rioja province. Its 28 Siemens Gamesa turbines have a combined installed capacity of 99.4 MW. The development is operated through Arauco Renovables within Parque Eólico Arauco; commercial authorisation began for a 92.3 MW portion in August 2025.In OperationArgentina
At a Glance
Declared capacity
92.3 MWTurbines
28Operator
Data coming soonCountry
ArgentinaLocation
-28.748°, -66.729°Website
Official project pageOwnership
2 records| Share | Organisation | Role | Details | Period |
|---|---|---|---|---|
| Unknown | Project Company | The June 2024 generation register identifies Arauco Renovables S.A.P.E.M. as the company for Arauco II phases III and IV, with CUIT 30-71540775-9. | Current / not dated | |
| Unknown | ![]() | Indirect Parent | Parque Eólico Arauco holds the development through its subsidiary Arauco Renovables, as described in the March 2026 green bond assessment. | Current / not dated |
Organisations
8 recordsOrganisations recorded as working on this asset or its project, and their role.
| Organisation | Role | Details |
|---|---|---|
| PEA III project company and operatorOwner Operator | Operates the Arauco II phases III and IV development within the Parque Eólico Arauco group. | |
| Provincial green bond financingFinance Insurance Legal | The March 2026 assessment describes provincial green bond proceeds passed to Parque Eólico Arauco to support its wind and solar developments, including Arauco II phases III and IV. | |
| Historical proposed financing assessmentFinance Insurance Legal | IDB Invest’s 2018 project disclosure considered financing for Arauco developments including phases III and IV and their shared transmission line. | |
P.EOLICO ARAUCO II R1.5 ET3y4 | Operator | Not set |
| PEA III developer and operating groupDevelopment And Operation | Develops and operates the PEA III wind project through its Arauco Renovables subsidiary. | |
| SG 3.4-132 turbine supplierTurbine Supply | The operator identifies 28 Siemens Gamesa SG 3.4-132 turbines configured at 3.55 MW each for PEA III. | |
| La Rioja Sur transmission interfaceGrid Connection | ENRE’s 2019 decision describes the shared Arauco connection to the La Rioja Sur substation in Transener’s transmission system. | |
| Regional transmission connection contextGrid Connection | ENRE’s 2019 grid access decision describes the Arauco II connection through the regional transmission system and the Arauco II substation. |
Supplier registration
Contact page onlyHow suppliers get onto this project's radar: its standing register, supplier portal or contact route.
General business enquiries can be made through the company’s published contact channel. This company-wide route does not provide project-specific supplier registration.
Parque Eólico Arauco company-wide contact information; no project-selectable supplier register is advertised on this page.
SourceChecked 28 Oct 2026
Capacity history
Recorded project capacity figures. Future-dated changes are shown but are not used as current capacity.
| Effective | Capacity type | Capacity | Source |
|---|---|---|---|
| 2 Aug 2025 | Declared capacity | 92.3 MW | Parque Eólico Arauco — commercially authorised portion from 2 August 2025 |