Gattendorf Nord II
Gattendorf Nord II onshore wind overview.
Gattendorf Nord II is a four-turbine wind farm in Burgenland, Austria. Construction began in late 2020 and the farm entered operation in 2021, using GE 5.3-158 turbines with a combined rated capacity of 21.2 MW.In OperationAustria
At a Glance
Capacity
21.2 MWTurbines
4Operator
Data coming soonCountry
AustriaLocation
48.029°, 16.998°Website
Official project pageOwnership
1 record| Share | Organisation | Role | Details | Period |
|---|---|---|---|---|
| Unknown | ![]() | Owner Operator | PÜSPÖK is the owner and operator of Gattendorf Nord II. | Current / not dated |
Organisations
2 recordsOrganisations recorded as working on this asset or its project, and their role.
| Organisation | Role | Details |
|---|---|---|
| Foundation supervision and EHS coordinationEngineering Consulting And Project Management | CES provided construction supervision of the piled foundations and foundation works, together with environmental, health and safety coordination for GE. Its stated assignment ran from March 2021 to October 2022. | |
| Turbine supplier and general contractorEpc Balance Of Plant | GE supplied four GE 5.3-158 wind turbines and acted as general contractor for Gattendorf Nord II. |
Supplier registration
Contact page onlyHow suppliers get onto this project's radar: its standing register, supplier portal or contact route.
Business enquiries can be submitted through PÜSPÖK’s general contact form. The form covers its wider project portfolio and includes technical project enquiries.
Portfolio-wide general contact form for PÜSPÖK, including technical project enquiries.