Mönchhof
Mönchhof onshore wind overview.
Mönchhof is an onshore wind installation on the Parndorfer Platte in Burgenland. It forms part of the wider Pannonia Gols and Mönchhof repowering development, which replaced older turbines and involved new foundations, access roads and electrical infrastructure.In OperationAustria
At a Glance
Capacity
16.5 MWTurbines
3Operator
Data coming soonCountry
AustriaLocation
47.901°, 16.961°Website
Official project pageOwnership
1 record| Share | Organisation | Role | Details | Period |
|---|---|---|---|---|
| Unknown | Developer | Windpark Mönchhof GmbH is named as a co-applicant for the Pannonia Gols and Mönchhof repowering project in the 2019 environmental assessment. | Current / not dated |
Organisations
8 recordsOrganisations recorded as working on this asset or its project, and their role.
| Organisation | Role | Details |
|---|---|---|
| Historical geotechnical consultantFoundation Design Context | Undertook ground investigation, geotechnical reports and foundation-related advice for the combined repowering development during 2019–2020. | |
| Repowering turbine technologyTurbine Supply Context | The 2019 environmental assessment specifies GE 5.5-158 turbines for the combined repowering scheme. | |
| Historical environmental-assessment consultantConsent And Environmental Assessment | Under its former name ImWind Operations GmbH, prepared the 2019 environmental assessment summary for Pannonia Gols and Mönchhof. | |
| Historical repowering civil-works contractorEpc Balance Of Plant | Carried out civil and electrical-infrastructure works as a partial general contractor in a consortium for PAGO, with construction from November 2019 to December 2021. | |
| Historical repowering promoterDevelopment | The European Investment Bank’s November 2019 project documentation names PK Windpark Management as promoter of Pannonia Gols and Mönchhof. | |
| Repowering developer and operator groupDevelopment And Operation | PÜSPÖK presents the operating Pannonia Gols development across Gols and Mönchhof in its renewable-generation portfolio. | |
| Electrical inspection contractorSurvey Inspection | Lists electrical inspections at the four-turbine Mönchhof wind farm in May 2026 among its completed references. | |
| Mönchhof repowering co-applicantProject Company And Consenting | Named as a co-applicant and client for the Mönchhof component of the combined repowering development. |
Supplier registration
Contact page onlyHow suppliers get onto this project's radar: its standing register, supplier portal or contact route.
General business enquiries can be submitted through the group’s contact page. The contact form provides a portfolio-wide starting point for engagement.
PÜSPÖK general business contact; this route is not a project-specific supplier register.
SourceChecked 29 Oct 2026