Veytaux
Veytaux pumped hydro overview.
Veytaux is the underground power-station complex of the Hongrin–Léman pumped-storage scheme in Vaud, Switzerland. It moves water between Lake Geneva and the Hongrin reservoir, around 880 metres higher. The original station and its 2017 extension provide 480 MW of installed generating machinery, with 60 MW held in reserve.In OperationSwitzerland
At a Glance
Installed capacity
480 MWEnergy storage
100,000 MWhOperator
Data coming soonCountry
SwitzerlandLocation
46.410°, 6.932°Website
Official project pageOwnership
6 records| Share | Organisation | Role | Details | Period |
|---|---|---|---|---|
| Unknown | Indirect Parent | Shareholder in FMHL, the company owning the Veytaux scheme. | Current / not dated | |
| Unknown | ![]() | Owner | Owns the Hongrin–Léman pumped-storage scheme, including the Veytaux power stations. | Current / not dated |
| Unknown | ![]() | Indirect Parent | Shareholder in FMHL, the company owning the Veytaux scheme. | Current / not dated |
| Unknown | Operator | Operates the scheme under mandate from FMHL. | Current / not dated | |
| Unknown | ![]() | Indirect Parent | Shareholder in FMHL, the company owning the Veytaux scheme. | Current / not dated |
| Unknown | ![]() | Indirect Parent | Shareholder in FMHL, the company owning the Veytaux scheme. | Current / not dated |
Organisations
8 recordsOrganisations recorded as working on this asset or its project, and their role.
| Organisation | Role | Details |
|---|---|---|
| Scheme managerDevelopment And Asset Management | Manages the scheme and production dispatch for FMHL. | |
| Veytaux II electromechanical supplierTurbine Supply | Supplied and installed the two 120 MW Pelton generating groups for the extension. | |
| Engineering partner, GIHLEM consortiumEngineering And Design | Participated in the GIHLEM engineering consortium for the Veytaux II extension. | |
| Engineering partner, GIHLEM consortiumEngineering And Design | Participated in the GIHLEM engineering consortium for the Veytaux II extension. | |
| Hydraulic modelling research partnerResearch And Monitoring | Provided physical hydraulic modelling for the design of the Veytaux II extension. | |
| Hydraulic modelling research partnerResearch And Monitoring | Provided physical hydraulic modelling for the design of the Veytaux II extension. | |
| Lead engineer, GIHLEM consortiumEngineering And Design | Participated in the GIHLEM engineering consortium for the Veytaux II extension. | |
| Plant operatorOperations Maintenance | Operates the Veytaux installations on behalf of FMHL. |
Supplier registration
Contact page onlyHow suppliers get onto this project's radar: its standing register, supplier portal or contact route.
Supplier enquiries can be directed through the scheme’s general contact form. Businesses can use this channel to introduce their capabilities and request the appropriate procurement contact.
General enquiries for the Hongrin–Léman scheme; the contact form is not a supplier register.
SourceChecked 30 Oct 2026
Capacity history
Recorded project capacity figures. Future-dated changes are shown but are not used as current capacity.
| Effective | Capacity type | Capacity | Source |
|---|---|---|---|
| Current | Installed capacity | 480 MW | FMHL — installed machinery including 60 MW reserve |