F.V. Anchoris
F.V. Anchoris solar overview.
Anchoris is a ground-mounted solar park in Carrizal, Luján de Cuyo, Mendoza. Its bifacial panels follow the sun on single-axis trackers and supply large industrial users through Argentina’s renewable-energy contract market. Genneia began commercial operation in August 2025 and formally inaugurated the park in February 2026.In OperationArgentina
At a Glance
Capacity
180 MWMounting
GroundOperator
Data coming soonCountry
ArgentinaLocation
-33.311°, -68.896°Website
Official project pageOwnership
1 record| Share | Organisation | Role | Details | Period |
|---|---|---|---|---|
| 100% | ![]() | Owner Operator | Genneia owns and operates Anchoris; its 2025 green-financing report records a 100% interest. | Current / not dated |
Organisations
14 recordsOrganisations recorded as working on this asset or its project, and their role.
| Organisation | Role | Details |
|---|---|---|
| Corporate construction-finance lenderFinance Insurance Legal | Provided a local-bank facility reported by Genneia among the loans supporting Anchoris, San Rafael and Trelew II. | |
| Corporate construction-finance lenderFinance Insurance Legal | Provided a local-bank facility reported by Genneia among the loans supporting Anchoris, San Rafael and Trelew II. | |
| Development-finance lenderFinance Insurance Legal | Participated in the 2024 corporate financing facility supporting Genneia’s Malargüe I and Anchoris solar developments. | |
| Connection-substation owner and transmission companyGrid Connection | Owns Anchoris substation, through which the solar park connects to the Argentine interconnected system. | |
| Original project developerHistorical Development Context | Originated the smaller Anchoris solar proposal that Genneia subsequently acquired and expanded. | |
GENNEIA RENOVABLES MATER | Operator | Not set |
| Solar-park developer, owner and operatorOwner Operator | Developed, built and operates the Anchoris solar park. | |
| Inverter manufacturerEquipment Supply | Huawei inverters are identified in Trackland’s Anchoris II and IV installation references. | |
| Panel manufacturerEquipment Supply | Jinko Solar panels are identified in Trackland’s completed Anchoris II and IV installation references. | |
| Development-finance lenderFinance Insurance Legal | Participated in the 2024 corporate financing facility supporting Genneia’s Malargüe I and Anchoris solar developments. | |
| Development-finance lenderFinance Insurance Legal | Participated in the 2024 corporate financing facility supporting Genneia’s Malargüe I and Anchoris solar developments. | |
| Solar-park cable supplierCables | Supplied cabling for Anchoris and worked with Genneia to recover cable drums after underground cable installation. | |
| Electromechanical installation contractorEpc Balance Of Plant | Installed trackers, panels and low-voltage electrical works for the construction groups identified as Anchoris II and Anchoris IV. | |
| Solar-tracker manufacturerEquipment Supply | Trina trackers are identified in Trackland’s Anchoris II and IV installation references. |
Equipment
4 recordsPanels and inverters recorded at this installation, with each unit's rating as its source gives it.
| Equipment | Manufacturer | Model | Units | Unit rating | Source |
|---|---|---|---|---|---|
| InvertersInstalled | Not setTrackland documents 60 inverters in its Anchoris II construction group, with work undertaken in December 2024–March 2025. | 60 | Not set | Source | |
| PanelsInstalled | Not setTrackland documents 30,240 panels in its Anchoris II construction group, with work undertaken in December 2024–March 2025. | 30,240 | Not set | Source | |
| InvertersInstalled | Not setTrackland documents 54 inverters in its Anchoris IV construction group, with work undertaken in March–May 2025. | 54 | Not set | Source | |
| PanelsInstalled | Not setTrackland documents 33,264 panels in its Anchoris IV construction group, with work undertaken in March–May 2025. | 33,264 | Not set | Source |
Supplier registration
Developer supplier portalHow suppliers get onto this project's radar: its standing register, supplier portal or contact route.
A portfolio-wide supplier page provides an invitation and onboarding documents for prospective suppliers. The separate supplier portal supports invoicing and payment administration for existing suppliers.
Genneia portfolio-wide supplier engagement; the invitation does not establish project-specific registration for Anchoris.
SourceChecked 28 Oct 2026