| In Construction | Grid connection developerAnholt | Substation Electrical | Offshore transformer platform and export connection to shore |
| In Operation | Grid infrastructure owner and operatorHorns Rev 1 | Cables | 36 kV inter-array gathering at Horns Rev Alpha and 150 kV export cable |
| In Operation | Offshore transmission owner and operatorHorns Rev 1 | Substation Electrical | Horns Rev Alpha offshore substation and 150 kV export connection |
| In Operation | Export cable and onshore cable delivery partyHorns Rev 2 | Cables | 42 km 150 kV submarine cable and 150 kV land cable to Endrup |
| In Operation | Grid connection owner and operatorHorns Rev 2 | Substation Electrical | Transformer platform, submarine export cable and onshore grid connection |
| In Construction | Export cable delivery leadHorns Rev 3 | Cables | 220 kV submarine export cable |
| In Construction | Transmission grid connection owner and developerHorns Rev 3 | Substation Electrical | Horns Rev 3 offshore transformer platform and grid connection |
| Consented | Grid connection works interfaceJammerland Bugt | Grid Connection | Jammerland Bugt connection at Asnæsværket high-voltage station |
| In Construction | Grid-connection principalKriegers Flak | Substation Electrical | Kriegers Flak Danish grid connection |
| Consented | Onshore grid infrastructure owner and operatorLillebælt Syd | Grid Connection | Lillebælt Syd onshore grid connection from high-voltage station Danfoss |
| In Construction | Offshore transmission customer and grid operatorRødsand II | Substation Electrical | Rødsand II offshore substation and transmission connection |
| In Operation | Offshore transmission owner and operatorRødsand II | Substation Electrical | Rødsand II offshore transmission assets |
| In Operation | Other | Onshore grid assets | Rødsand II · Final Grid Connection Point |