| Consented | Export cable transport and installation consortium partnerBałtyk 2 | Cables | Four 220 kV HVAC export cables for Baltyk II and Baltyk III |
| Consented | Export cable transport and installation consortium partnerBałtyk 3 | Cables | Four 220 kV HVAC export cables for Baltyk II and Baltyk III |
| In Construction | Haliade demonstration cable burial and scour-protection contractorBelwind | Marine Vessels Logistics | Cable excavation, erosion protection and fall-pipe vessel works |
| In Construction | Haliade demonstration cable installation contractorBelwind | Cables | Array cable from the Haliade demonstration turbine to the Belwind substation |
| In Construction | Haliade demonstration cable burial and scour-protection contractorBelwind Haliade Demonstration | Marine Vessels Logistics | Cable excavation, erosion protection and fall-pipe vessel works |
| In Construction | Haliade demonstration cable installation contractorBelwind Haliade Demonstration | Cables | Array cable from the Haliade demonstration turbine to the Belwind substation |
| In Construction | Turbine installation contractorBlyth Offshore | Transport Installation | Installation of five MHI Vestas turbines using Vole au Vent |
| In Construction | Monopile foundation transport and installation contractorBorkum Riffgrund II | Foundations | 36 monopile foundations |
| In Construction | Monopile foundation transport and installation contractorBorkum Riffgrund III | Foundations | Borkum Riffgrund 3 83 monopile foundation installation campaign |
| In Construction | Export and inter-array cable installation contractorBurbo Bank Extension | Cables | Export cable and 32 infield cables |
| In Operation | Five-year O&M consortium memberChanghua Demonstration | Operations Maintenance | First five years of operation and maintenance for TPC Changhua Phase 1 |
| In Construction | Foundation design, fabrication and installation contractorChanghua Demonstration | Foundations | 84 pin piles and 21 jacket foundations for Changhua Phase 1 |
| Consented | Main consortium contractor and balance-of-plant leadChanghua Demonstration | Epc Balance Of Plant | 109.2 MW Changhua Offshore Wind Farm Project |
| In Construction | Onshore and offshore cable supplier and installerChanghua Demonstration | Cables | Four medium-voltage export cables and onshore/offshore cable systems |
| In Construction | Onshore substation upgrade contractorChanghua Demonstration | Substation Electrical | Da Cheng onshore substation electrical equipment, SCADA and emergency-power upgrade |
| In Construction | Wind turbine installation vessel providerChanghua Demonstration | Transport Installation | Installation of 21 Hitachi 5.2 MW offshore wind turbines using jack-up vessel Taillevent |
| In Construction | Foundation and turbine transport and installation contractorCoastal Virginia Offshore Wind Pilot Project | Transport Installation | Two CVOW pilot foundations and turbines |
| In Operation | Reservoir extension civil works partnerCoo | Epc Balance Of Plant | Joint venture civil works described in May 2021. |
| In Construction | Export cable installation contractorCrossWind | Cables | Hollandse Kust Noord grid-connection subsea cables |
| In Construction | Wind turbine installation contractorDieppe - Le Tréport | Transport Installation | 62 Siemens Gamesa turbines for Dieppe-Le Tréport |
| In Construction | Turbine transport and installation contractorDogger Bank A | Transport Installation | GE Haliade-X turbine transport and installation for Dogger Bank A and B |
| In Construction | Wind turbine transport and installation contractorDogger Bank B | Transport Installation | GE Haliade-X turbine transport and installation for Dogger Bank B |
| In Construction | Wind turbine transport and installation contractorDogger Bank C | Transport Installation | 87 GE Haliade-X 14 MW turbines for Dogger Bank C |
| In Construction | Phase 2 foundation installation contractorFormosa 1 OWF | Foundations | Twenty foundations for Formosa 1 Phase 2 |
| In Construction | Phase 2 offshore EPCI and main contractorFormosa 1 OWF | Epc Balance Of Plant | 120 MW Formosa 1 Phase 2 offshore foundations, cables and construction support |
| In Construction | Foundation and subsea cable EPCI contractorFormosa 2 OWF | Epc Balance Of Plant | 47 jacket foundations, 188 pin piles, four export cables and 47 inter-array cables |
| In Construction | Underwater noise and marine mammal monitoring managerFormosa 2 OWF | Consenting Environmental | Foundation installation environmental compliance monitoring |
| In Construction | Foundation and offshore substation transport and installation contractorGode Wind 3 | Foundations | 107 monopile foundations and one offshore substation foundation/topside for Gode Wind III and Borkum Riffgrund 3 |
| In Construction | Export cable transport and installation contractorHornsea Project Three | Cables | Hornsea 3 offshore export cable transport, installation and protection |
| In Operation | Monopile foundation transport and installation contractorInch Cape | Foundation And Marine Works | 54 monopile foundations for Inch Cape |
| In Construction | Foundation design, construction and installation contractorKårehamn | Foundations | 16 gravity-based foundations |
| In Construction | Marine installation and seabed preparation contractorKårehamn | Transport Installation | Seabed preparation, foundation installation, ballasting and scour protection |
| In Construction | Offshore high-voltage-station foundation contractorKriegers Flak | Substation Electrical | Two gravity-based foundations for offshore high-voltage stations |
| In Construction | Turbine transport and installation contractorKriegers Flak | Transport Installation | 72 Siemens Gamesa turbines |
| In Operation | Export cable reburial contractorLuchterduinen | Cables | 25 km 150 kV export cable reburial |
| In Construction | EPCI balance-of-plant contractorNobelwind | Epc Balance Of Plant | 51 monopile foundations, scour protection, OHVS foundation and turbine installation package |
| In Construction | Export cable installation contractorNobelwind | Cables | Pre-installed export cable connecting Nobelwind to the Belgian grid |
| In Construction | Monopile foundation design, fabrication and installation contractorNobelwind | Foundations | 50 wind turbine foundations and one OHVS foundation |
| In Construction | Turbine and foundation installation contractorNobelwind | Transport Installation | Vidar jack-up installation vessel and Ostend marshalling harbour |
| In Construction | Wind turbine installation contractorNoirmoutier | Turbine Supply | 61 Siemens Gamesa turbines for EMYN |
| Consented | Inter-array cable installation contractorNordlicht I | Cables | 196 kilometres of inter-array cables for Nordlicht I and II |
| Consented | Inter-array cable installationNordlicht II | Cables | Nordlicht II offshore wind project |
| In Operation | Offshore grid connection cable transport, installation and protection contractorNordsee Cluster A - N-3.7 | Cables | Three 155 kV HVAC cables linking N-3.7/N-3.8 to DolWin kappa |
| Consented | Offshore grid-connection cable transport, installation and protection contractorNordsee Cluster A - N-3.8 | Cables | 155 kV HVAC grid-connection cables linking N-3.7 and N-3.8 to DolWin kappa |
| In Construction | Cable transport and installation contractorNorthwester 2 | Cables | Northwester 2 cable installation package |
| In Construction | EPCI contractorNorthwester 2 | Epc Balance Of Plant | Northwester 2 foundations, cables and turbine installation |
| In Construction | Foundation design, procurement and installation contractorNorthwester 2 | Foundations | 23 turbine monopile foundations |
| In Construction | Turbine installation contractorNorthwester 2 | Transport Installation | 23 V164-9.5 MW wind turbine generators |
| In Construction | Export cable installation contractorNorthwind | Cables | 43 km 245 kV export cable and 14 km land cable |
| Consented | Foundation and turbine transport and installation contractorOranjeWind | Transport Installation | OranjeWind monopile foundation and wind turbine installation using Les Alizes and Voltaire |
| In Construction | Foundation and turbine installation vessel contractorPori-Tahkoluoto | Transport Installation | Installation of ten gravity-based foundations and ten turbines using Vole au vent |
| In Construction | Principal marine construction contractorPori-Tahkoluoto | Epc Balance Of Plant | Dredging, seabed construction, foundation installation and wind-turbine installation |
| In Operation | Inter-array cable replacement prime contractorPrinses Amalia | Cables | Replacement of an inter-array cable at Prinses Amalia |
| In Construction | Offshore export cable installation contractorRace Bank | Cables | Offshore export cables from offshore substations to shore |
| In Construction | Wind turbine transport and installation contractorSaint-Nazaire | Transport Installation | 80 6 MW wind turbine generators |
| In Operation | Cable package consortium memberThor | Cable Supply And Installation Context | Thor export, inter-array and onshore cables |
| In Operation | Foundation installation vessel providerThor | Foundation And Marine Works | Thor foundation installation works |
| In Construction | TWB II export cable installerTrianel Windpark Borkum | Cables | Export cable installation connecting Trianel Windpark Borkum II to the TenneT grid |
| In Construction | TWB II turbine installation contractorTrianel Windpark Borkum | Transport Installation | Transport and installation of 32 Senvion turbines |
| In Construction | Turbine transport and installation contractorVesterhav Nord | Transport Installation | Transport and installation of 41 turbines across Vesterhav Nord and Syd |
| In Construction | Turbine transport and installation contractorVesterhav Syd | Transport Installation | Transport and installation of 41 turbines across Vesterhav Nord and Syd |
| In Operation | Other | Onshore grid assets | Dogger Bank C · Onshore Conversion |
| In Operation | Other | Onshore grid assets | Dogger Bank C · Final Grid Connection Point |
| In Operation | Other | Onshore grid assets | Saint-Nazaire · Final Grid Connection Point |