The Meitingen substation battery is a stand-alone lithium-ion energy storage installation in Bavaria. Developed jointly by Lechwerke and Bayernwerk Natur, it uses two battery containers and an existing reserve grid connection provided by SGL Carbon. The installation trades flexibility in electricity and balancing markets, with LEW Natur recorded as its current operator.In OperationGermany
At a Glance
Capacity
7.6 MWEnergy storage
7.4 MWhStorage duration
0.9 hoursStorage type
StandaloneOwners
Bayernwerk Natur GmbH +2 moreOperator
Data coming soonCountry
GermanyLocation
48.548°, 10.864°Website
Official project pageOwnership
3 records| Share | Organisation | Role | Details | Period |
|---|---|---|---|---|
| Unknown | Co Developer | Bayernwerk Natur developed the battery jointly with Lechwerke and led the technical work described in the July 2023 launch announcement. | Current / not dated | |
| Unknown | Co Developer | Lechwerke developed the battery jointly with Bayernwerk Natur; the July 2023 announcement also describes joint operation and equal investment contributions. | Current / not dated | |
| Unknown | Operator | The Marktstammdatenregister identifies LEW Natur GmbH as operator and records the operator change on 1 October 2024. | From Oct 2024 |
Organisations
6 recordsOrganisations recorded as working on this asset or its project, and their role.
| Organisation | Role | Details |
|---|---|---|
| Technical project leadEngineering And Technical | Led the technical work on the jointly developed Meitingen battery, according to the July 2023 project announcement. | |
| Battery flexibility tradingOfftake And Market | Lechwerke’s trading team markets the battery in intraday electricity and balancing markets, as described at its July 2023 launch. | |
LEW Natur GmbH | Operator | Not set |
| Registered battery operatorOwner Operator | Recorded as operator of battery unit SEE949834584921, following the operator change dated 1 October 2024. | |
| Distribution network operatorGrid Connection | The Marktstammdatenregister identifies LEW Verteilnetz as the battery’s connection network operator. | |
| Reserve grid connection providerGrid Connection | Provided an existing reserve network connection at its Meitingen site for use by the battery. |
Supplier registration
Contact page onlyHow suppliers get onto this project's radar: its standing register, supplier portal or contact route.
Commercial enquiries can be made through the developer’s general contact page. Its procurement page publishes purchasing conditions and documents for contractors.
Lechwerke-wide contact and purchasing information; these pages do not establish a Meitingen-specific supplier register.
SourceChecked 28 Oct 2026