Collie Battery (Neoen)
Collie Battery (Neoen) battery storage overview.
Neoen's Collie Battery is a four-hour storage installation in Western Australia's South West Interconnected System. Its two operating stages use Tesla Megapack systems to store electricity and deliver grid-reliability services. Stage 1 began operating in October 2024 and Stage 2 in July 2025; the larger consented development allows for further expansion.In OperationAustralia
At a Glance
Capacity
560 MWEnergy storage
2,240 MWhStorage duration
4 hoursStorage type
StandaloneOwner
NeoenOperator
Data coming soonCountry
AustraliaLocation
-33.310°, 116.293°Website
Official project pageOwnership
1 record| Share | Organisation | Role | Details | Period |
|---|---|---|---|---|
| Unknown | Owner Operator | Neoen owns and operates the two completed stages of Collie Battery. | Current / not dated |
Organisations
12 recordsOrganisations recorded as working on this asset or its project, and their role.
| Organisation | Role | Details |
|---|---|---|
| Instrument transformer manufacturerEquipment Supply | Arteche supplied the current and voltage transformer technology selected for the battery connection. | |
| Grid reliability service counterpartyOfftake Revenue | AEMO contracted grid-reliability services from the battery under separate agreements for Stage 1 and Stage 2. | |
| Portfolio financing participantFinance Insurance Legal | CEFC financing for Neoen's Australian portfolio supported development of Collie Battery Stage 2. | |
| Transmission network connection providerGrid Connection | Western Power provides the transmission network connection for the battery. | |
| Connection equipment supplierEquipment Supply | GFF Power supplied and supported high-voltage instrument transformers for the battery's transmission connection. | |
| Battery owner and operatorOwner Operator | Neoen owns and operates Collie Battery's two completed stages. | |
| Development and asset management providerDevelopment And Asset Management | Neoen Australia provides project development, construction management and asset management for Collie Battery. | |
| Battery technology supplierEquipment Supply | The completed installation comprises 572 Tesla Megapack 2XL units. | |
| Storage operations and maintenance partnerOperations Maintenance | The March 2026 project factsheet names Tesla as a storage operations and maintenance partner. | |
| Construction and balance-of-plant contractorEpc Balance Of Plant | UGL delivered construction, substation works, battery installation and associated balance-of-plant infrastructure. | |
| Storage operations and maintenance partnerOperations Maintenance | The March 2026 project factsheet names UGL as a storage operations and maintenance partner. | |
| Environmental and social assessment adviserConsenting Environmental | Umwelt prepared environmental, noise and community-engagement assessments supporting the development application. |
Supplier registration
Register closedHow suppliers get onto this project's radar: its standing register, supplier portal or contact route.
The project's published supplier-interest listing has closed. General enquiries can be directed through the project contact page.
The project-specific ICN listing for Collie Battery has closed; the project contact page remains available for general enquiries.
SourceChecked 27 Oct 2026