Gannawarra Energy Storage System
Gannawarra Energy Storage System battery storage overview.
Gannawarra is a lithium-ion battery near Kerang in Victoria, integrated with the neighbouring solar farm through shared electrical infrastructure. Commercial operation began in November 2018, with EnergyAustralia managing charging and dispatch under a long-term storage-services agreement.In OperationAustralia
At a Glance
Capacity
25 MWEnergy storage
50 MWhStorage duration
2 hoursStorage type
Co Located RenewableOwners
Edify Energy Pty Ltd +3 moreOperator
Data coming soonCountry
AustraliaLocation
-35.734°, 143.780°Website
Official project pageOwnership
4 records| Share | Organisation | Role | Details | Period |
|---|---|---|---|---|
| 50.9% | Co Owner | Gentari’s battery project page identifies Edify Energy’s beneficial co-ownership interest. The battery’s direct legal owner is GESS ProjectCo. | Current / not dated | |
| Unknown | Designated Operator | EnergyAustralia manages battery charging and dispatch under the storage-services agreement through 2030. | Current / not dated | |
| 49.1% | Co Owner | Gentari’s battery project page identifies its beneficial co-ownership interest. The battery’s direct legal owner is GESS ProjectCo. | Current / not dated | |
| Unknown | Owner Operator | GESS ProjectCo is the licensed generation company and legal owner of the Gannawarra battery. | Current / not dated |
Organisations
17 recordsOrganisations recorded as working on this asset or its project, and their role.
| Organisation | Role | Details |
|---|---|---|
| Original balance-of-plant construction contractorEpc Balance Of Plant | The 2018 licence application appointed RCR O’Donnell Griffin to construct and connect the battery balance of plant, with initial maintenance responsibilities. | |
| Generator performance and market integration authorityGrid And Tender Context | The 2018 licence application documents AEMO’s assessment of the battery’s generator performance standards and market registration arrangements. | |
| Public grant funding partnerPublic Funding And Award | ARENA supported the Gannawarra battery alongside the Victorian Government. | |
| Development technical adviserTechnical Advisory | The 2018 licence application identifies DIgSILENT Pacific as providing technical advice and due diligence during development, design and financing. | |
| Developer and asset managerDevelopment And Asset Management | Edify developed and manages the Gannawarra battery. | |
| Market intermediary and dispatch operatorOfftake And Market | EnergyAustralia manages charging, dispatch and market participation under the battery storage-services agreement through 2030. | |
| Local planning authorityConsenting And Planning | The 2018 licence application records the council’s endorsement of plans incorporating the battery within the solar farm’s approved footprint. | |
| Shared network operator and site sublessorGrid Connection | The solar farm company provides the battery’s shared network infrastructure and site sublease. | |
| Co-owner and original investment partnerOwnership History | Gentari’s Australian business, formerly WIRSOL Energy, is a co-owner of the battery. | |
| Original development and construction companyHistorical Development Context | The 2018 licence application assigns development, construction and grant responsibilities to GESS DevCo. | |
| Historical project holding companyOwnership History | The 2018 licence application identifies GESS HoldCo as the sole shareholder of GESS ProjectCo. | |
| Licensed battery generation companyOwner Operator | GESS ProjectCo holds the generation licence for the Gannawarra battery. | |
| Historical corporate freehold landownerLease Award And Site Control | The 2018 licence application names Greg and Faye Fowler Pty Ltd as the freehold landowner under the headlease supporting the battery’s site sublease. | |
| External distribution network operatorGrid Connection | The battery’s shared solar-farm network interfaces with the Powercor distribution network. | |
| Development technical assurance adviserTechnical Advisory | The 2018 licence application names RINA SERVICES S.p.A. as providing technical support, advice and due diligence. | |
| Original battery supplier and maintenance counterpartyEquipment Supply | Tesla supplied the original battery and entered into the long-term maintenance agreement described in the 2018 licence application. | |
| State funding and programme partnerFunding And Programme | The Victorian Government supported the battery through the Victorian Energy Storage Initiative. |
Supplier registration
Contact page onlyHow suppliers get onto this project's radar: its standing register, supplier portal or contact route.
Supplier enquiries can use the developer’s corporate partner contact route. Engagement is through a company-wide enquiry route.
Edify’s corporate partner page addresses contractors, equipment suppliers and service providers across its portfolio; it is not a Gannawarra-specific register.
SourceChecked 28 Oct 2026