Limondale Battery
Limondale Battery battery storage overview.
Limondale Battery is an eight-hour energy storage installation near Balranald in New South Wales, beside the Limondale solar farm. Its 144 Tesla Megapacks provide long-duration storage, with full-capacity operation announced in May 2026.In OperationAustralia
At a Glance
Consented capacity
200 MWEnergy storage
400 MWhStorage duration
8 hoursStorage type
Co Located RenewableOwner
Limondale Battery Pty. Ltd.Operator
Data coming soonCountry
AustraliaLocation
-34.769°, 143.535°Website
Official project pageOwnership
1 record| Share | Organisation | Role | Details | Period |
|---|---|---|---|---|
| Unknown | Owner | Limondale Battery Pty Ltd owns the battery energy storage system and its dedicated connection asset. The neighbouring solar farm has a separate project company. | Current / not dated |
Organisations
8 recordsOrganisations recorded as working on this asset or its project, and their role.
| Organisation | Role | Details |
|---|---|---|
| Long-term energy service agreement programmeFunding And Programme | AEMO Services supported the battery through the New South Wales long-term energy service agreement programme. | |
| Market registration and operating approvalGrid Connection | AEMO registered the battery and provided the operating sign-off reported in May 2026. | |
| Balance-of-plant delivery partnerEpc Balance Of Plant | Beon delivered the battery's balance-of-plant works, including civil, structural, electrical and control systems. | |
| Biodiversity management consultantConsenting And Environment | Biosis prepared biodiversity management material for the battery development. | |
| Connection infrastructure providerGrid Connection | Lumea provides the designated network infrastructure serving the battery and neighbouring solar farm. The battery's dedicated connection asset belongs to its project company. | |
| Battery developer and project managerDevelopment And Asset Management | RWE's Australian renewables business developed the Limondale battery and manages the project within its Australian portfolio. | |
| Megapack battery supplierEquipment Supply | Tesla supplied the Megapack battery system comprising 144 units. | |
| Transmission connection and commissioning partnerGrid Connection | Transgrid supported the transmission connection and provided sign-off for the battery to operate at full capacity. |
Supplier registration
Contact page onlyHow suppliers get onto this project's radar: its standing register, supplier portal or contact route.
Supplier enquiries can be directed through the project's public contact channel. The page provides a general enquiry route for engagement.
The Limondale battery project page provides a general project contact channel. No project-specific supplier registration form is provided on that page.
SourceChecked 27 Oct 2026
Capacity history
Recorded project capacity figures. Future-dated changes are shown but are not used as current capacity.
| Effective | Capacity type | Capacity | Source |
|---|---|---|---|
| 7 Oct 2022 | Consented capacity | 200 MW | NSW — maximum permitted battery output under SSD-8025-MOD-2 |
| Current | Other capacity | 100 MW | RWE — registered maximum charging power, 27 May 2026 |