SMAREG14 Lößnitz
SMAREG14 Lößnitz battery storage overview.
SMAREG14 is a lithium-ion battery storage installation in Lößnitz, Saxony. It entered operation in March 2026 and connects to the regional medium-voltage electricity network. The installation has a registered output of 9.8 MW and usable storage energy of 20.58 MWh.In OperationGermany
At a Glance
Capacity
9.8 MWEnergy storage
20.6 MWhStorage duration
2.1 hoursStorage type
UnknownOwners
ju:niz Energy GmbH +1 moreOperator
Data coming soonCountry
GermanyLocation
50.617°, 12.719°Website
Official project pageOwnership
2 records| Share | Organisation | Role | Details | Period |
|---|---|---|---|---|
| Unknown | ![]() | Developer | The municipal construction report identifies ju:niz as the private investor developing the Lößnitz battery project. | Current / not dated |
| Unknown | Operator | SMAREG 14 is the registered operator of the Lößnitz battery storage installation. | Current / not dated |
Organisations
4 recordsOrganisations recorded as working on this asset or its project, and their role.
| Organisation | Role | Details |
|---|---|---|
| Battery project developer and investorDevelopment | ju:niz developed the Lößnitz battery project described in the municipality’s December 2025 construction report. | |
| Medium-voltage network operatorGrid Connection | Mitteldeutsche Netzgesellschaft Strom is the network operator recorded for the battery’s medium-voltage connection. | |
SMAREG 14 GmbH & Co. KG | Operator | Not set |
| Registered battery operatorOwner Operator | SMAREG 14 is named as the operating company in the public electricity asset register. |
Supplier registration
Contact page onlyHow suppliers get onto this project's radar: its standing register, supplier portal or contact route.
Supplier enquiries can use the developer’s general contact page. Engagement covers the wider company portfolio.
The ju:niz company contact form is portfolio-wide and separate from a Lößnitz-specific supplier register.
SourceChecked 28 Oct 2026