Supernode Battery (Stage 2)
Supernode Battery (Stage 2) battery storage overview.
Supernode Stage 2 is a four-hour battery installation at Brendale, Queensland, beside the South Pine switchyard. It entered commercial operation in July 2026 under a long-term tolling agreement with Origin Energy and forms a separate stage of the wider Supernode energy and digital infrastructure campus.In OperationAustralia
At a Glance
Technical capacity
259.9 MWEnergy storage
1,238 MWhStorage duration
4 hoursStorage type
StandaloneOwners
Quinbrook Infrastructure Partners +1 moreOperator
Data coming soonCountry
AustraliaLocation
-27.317°, 152.971°Website
Official project pageOwnership
2 records| Share | Organisation | Role | Details | Period |
|---|---|---|---|---|
| Unknown | Developer | Developer and investment sponsor of Supernode Stage 2. | Current / not dated | |
| Unknown | Operator | AEMO identifies Supernode Operations Pty Ltd, acting as trustee for Supernode BESS 1 Project Trust, for generating unit SNB02. | Current / not dated |
Organisations
9 recordsOrganisations recorded as working on this asset or its project, and their role.
| Organisation | Role | Details |
|---|---|---|
| Electrical construction and commissioningEpc Balance Of Plant | All Energy Contracting was awarded the Stage 2 construction package for HV and DC cabling, electrical installation, earthing, testing and commissioning. | |
| Battery lifecycle servicesOperations Maintenance | CATL's long-term service agreement supports monitoring, fault response and preventive maintenance across its Supernode storage systems. | |
| Battery storage system supplierEquipment Supply | CATL supplied EnerC Plus systems for Supernode Stages 1 and 2. | |
| Battery system integrationEquipment Supply | GE Vernova was selected as the Stage 2 BESS integration provider in September 2024. | |
| Electrical construction clientEngineering And Infrastructure | All Energy Contracting identifies this company as a client for its Brendale Supernode electrical construction work covering the first two stages. | |
| Long-term battery tollingOfftake Revenue | Origin Energy has contracted the capacity of Stage 2 under a 12-year tolling agreement. | |
| Project delivery and asset managementDevelopment And Asset Management | Private Energy Partners supported design, procurement and construction and oversees longer-term asset management. | |
| Electrical construction clientEngineering And Infrastructure | All Energy Contracting identifies this company as a client for its Brendale Supernode electrical construction work covering the first two stages. | |
| Transmission connection partnerGrid Connection | Powerlink reports successful energisation of the first two Supernode stages. |
Supplier registration
Contact page onlyHow suppliers get onto this project's radar: its standing register, supplier portal or contact route.
Suppliers can submit a general enquiry through the campus website. A published supplier code sets expectations for engagement, without a project-specific registration form.
The Supernode website provides a general enquiry form for the campus, including Stage 2. Its supplier code of conduct sets expectations for suppliers without providing project-specific registration.
SourceChecked 28 Oct 2026
Capacity history
Recorded project capacity figures. Future-dated changes are shown but are not used as current capacity.
| Effective | Capacity type | Capacity | Source |
|---|---|---|---|
| Current | Technical capacity | 259.9 MW | AEMO July 2026 — SNB02 AC nameplate capacity |